Project Initiator Information

Open Joint-Stock Company “Magnitogorskiy Metallurgical Kombinat”

OJSC “MMK”

93, Kirova Str., Magnitogorsk town, Chelyabinsk region, 455002

Company executive

Viktor Phillipovich Rashnikov

Lines of business of the organization

Ore-dressing processing;

Metallurgical treatment;

Power supply;

Refractory industry.

Brief description of the project

Production of the highly-profitable hot-rolled plate with thickness from 8 up to 160 mm for oil-and-gas industry, shipbuilding, boiler building, machine building

Total cost of the project

463 million Euro

Required investment

463 million Euro

Payback period of the project (years)

3 years

Project documents

-

Current project status

Building phase

Expected forms of cooperation

-

Contact person

Alexander Yuryevich Permyakov – head of the investment management department

Waiting room: +7 (351)9- 24-45-12

Office phone: +7 (351)9- 24-67-79

Fax: +7 (351)9-24-68-81